ARTICLE VI
SECTION 25.29 EARTH
MATERIAL REMOVAL, FILLING, EXCAVATION
A.
GENERAL PROVISIONS
1. No owner, developer, excavator or other
person shall dig, excavate, scrape or otherwise disturb nor move or cause,
allow, permit or suffer to be moved the soil or carry on filling operations on
any premises in the city, unless and until after an application for a Temporary
Special Exception from the Commission is obtained. A Temporary Special Exception may be granted by the Commission,
subject to the requirements of this Section and subject to conditions deemed
necessary to prevent damage to other property and to protect the health, safety
and general welfare of the public.
B. EXEMPTIONS
A Special Exception is
not required in connection with the following excavation, grading, removal or
filling operations:
1. Any
Subdivision, Special Exception use and/or site plan approved by the Planning
and Zoning Commission;
2. Any
excavation, grading, removal or filling of an area ˝ acre or less in size;
3.
Necessary foundation and trench work on a lot for which a Zoning Permit
and a Building Permit have been issued and then not exceeding ˝ acre;
4.
Plowing, spading, cultivating, harrowing of soil or any operation
ordinarily associated with the tilling of the soil for agricultural or
horticultural purposes;
5. Any
operations for the purposes of soil and conservation as defined or prescribed
by Soil Conservation Service of the United States Department of Agriculture;
6.
Necessary filling, excavation, grading and/or removal in connection with
resurfacing of an existing roadway, sidewalk or parking lot, the removal of
excess soil resulting from the construction and/or alteration of public streets
and ways including sidewalks;
7. Any
building or improvement carried out by the City of Derby
8.
Conduct of a sanitary landfill by the City of Derby
9. Stock
piling of street maintenance material required by the City of Derby
10.
Regrading or filling as part of a landscaping project on an individual
residential lot of less than ˝ acre and when such operation is not for
commercial purposes and then not exceeding 300 cubic yards of material in any
calendar year.
C. APPLICATION
PROCEDURE AND REQUIREMENTS
The owner shall clearly
delineate the place or places from which the earth material is sought to be
removed or deposited. The application
shall also specify the number of cubic yards of soil to be removed or filled,
the length of time necessary to do so, and a concise statement indicating why
it is essential and necessary to the development of the property to remove or
deposit and/pr remove such amount of earth material, and a narrative
description of measures to be taken to minimize the erosion of soil and the
depositing of sediments both during the activity and after completion. Erosion and sediment control plans shall
conform to standards prescribed in “Connecticut Guidelines for Soil Erosion and
Sediment Control” (1985) as amended.
Copies of the guidelines are available from the office of the New Haven
County Soil and Water Conservation District.
Alternate Principles, Methods and Practices may be used subject to
review by the City Engineer and approval by the Commission. The Commission shall schedule and conduct a
public hearing on such application in accordance with the applicable provisions
of the General Statutes.
D. GENERAL
CONSIDERATIONS
The Commission may,
upon application, authorize the issuance of a Temporary Special Exception for
earth material removal, filling or excavation.
In authorizing the issuance of a Temporary Special Exception, the
Commission shall take into consideration the public health, safety and welfare;
and shall prescribe appropriate conditions and safeguards to insure the
accomplishment of the following objectives:
1. All proposed structures, equipment or
material shall be readily accessible for fire, police and other emergency
protection.
2. The proposal shall be of such location, size
and character that it will be in harmony with appropriate and orderly
development of the zone, the neighborhood and the City; and will not be
detrimental to established properties in the area conflict with the traffic
characteristics of the neighborhood.
3. The location and size of such proposal, the
nature and intensity of operations involved in or conducted in connection with
such proposal, its site layout, and its relation to access streets shall be
such that both pedestrians and vehicular traffic to, from and in the vicinity
of the use will not be hazardous, inconvenient or detrimental to the character
of the zone or conflict with the traffic characteristics of the neighborhood.
4. The nature and extent of landscaping and
excavation on the site shall be such that the use will not hinder or discourage
the appropriate development and use of adjacent land or buildings or impair the
value thereof.
E. APPLICATION
AND PROCEDURE
Application for a
Special Exception under this Section shall be submitted, in writing, with an
application prescribed by the Commission.
The Commission may request the applicant to submit such additional
information that it deems necessary in order to decide on the application. In acting on any application, the Commission
shall hold a public hearing, shall decide thereon and shall give notice of its
decision as required by law. The
application shall be signed by the owner or his authorized agent, where the
excavation, grading, removal or filling operation is proposed and shall be
accompanied by maps and plans, drawn to a scale of 1” = 50’, with profiles on
the longitudinal axis 200 feet on center or closer if required by the
Commission, prepared by a licensed surveyor or engineer and showing the
following:
1. Zoning district for the lot, the City
Assessor’s map and lot number for the lot and the acreage of the lot;
2. The quantity in cubic yards of earth
material involved in project;
3. A small scale map, drawn to the same scale
as the City Assessor’s map of the area, showing the location of the lot, the
names of all owners within 500 feet and streets and the names of the applicant
and the owner of the lot;
4. In the area of the proposed operation and
within 200 feet thereof, existing contours and the proposed contours for the
completed operation, which contours shall have a maximum interval of two (2)
feet;
5. The grades of all abutting streets and
lands;
6. Location and size of any existing and
proposed building or structures on the lot;
7. Proposed slopes and lateral supports at
limits of project upon completion;
8. Proposed travel access to the area of the proposed
operation;
9. Location of rivers, streams, brooks,
waterways, lakes, ponds, marshes, swamps, bogs, flood plains and wooded areas
on and adjacent to the lot;
10. Details of existing and proposed drainage
systems and proposed measures for erosion and sedimentation control, and
details of proposed planting for the area of the proposed operation, both to
prevent erosion during the course of the operation and at the conclusion
thereof;
11. The location and limits of the area of the
proposed operation;
12. The proposed details of entry and egress for
surface water drainage and of any streams, bodies of water, and watercourses,
natural or artificial. Filling
operations must be conducted in such a manner as not to alter the course of
rivers, streams, or other waterbodies unless approved by the Inland/Wetlands
Commission or in the case of waterbodies with encroachment lines by the State
of Connecticut, Department of Environmental Protection;
13. Clearing, grading, vegetative stabilization;
a.) areas to be cleared, staging and sequence of
clearing;
b.) disposal of cleared material;
c.) areas to be graded, staging and sequence of
grading;
d.) areas and acreage to be vegetatively
stabilized;
e.) planned vegetation with details of plants,
seed, mulch, fertilizer planting dates, etc.;
f.) temporary erosion protection of disturbed
areas;
g.) temporary erosion
protection when time of year or weather prohibit establishment of permanent vegetative cover.
14. Typed
narrative addressing the following:
(written provisions for soil erosion contingency plans)
a.) Nature, purpose and description of project;
b.) Potentially serious erosion or sediment
problems;
c.) The stages of development if more than one
stage is planned;
d.) The sequence of major
operations on the land, such as installation of erosion control measures,
clearing, grading, temporary stabilization, road base, road paving, building
construction, permanent stabilization, removal of temporary erosion control
measures;
e.) The time required for the major operations
identified in the sequence;
f.) Maintenance requirements or measures during
construction of project;
g.) Person responsible for maintenance during
construction of project;
h.) Maintenance requirements of permanent measures
when project is complete;
i.) Organization or person responsible for
maintenance of permanent measures when project is complete;
j.) Certification that proposed work nor
progress of work will have any impact on an Inland Wetland or that of a previously
obtained Inland Wetland permit.
F. GENERAL REQUIREMENTS
The Commission may
grant a Special Exception for a maximum period of two (2) years, when it is
satisfied that the following requirements will be met:
1. The applicant shall be required to section
the entire property which is the subject of his permit into areas of not more
than five (5) acres and he shall so schedule the work of soil removal or
filling so that the operation conducted in one section shall be complete and
the section shall be at final grade before work shall commence in any other
section of the premises.
2. When the operation of each section is
completed, or work has progressed sufficiently to where reclamation is
practicable, the area affected by the operation shall then be graded so that
slopes in disturbed areas shall be no steeper than 1:2
(vertical-horizontal). A layer of
topsoil shall be spread over the compaction in accordance with the approved
final grading plan. The area shall then
be seeded with a suitable grass mixture at the minimum rate of 5 lbs. Per 1,000
square feet containing at least 75% permanent grasses and maintained by
mulching, repairing and reseeding until the area is stabilized and approved by
the Commission. Any permitted operation
that remains inactive for 30 days or more shall be graded to no steeper than a
1:2 (vertical-horizontal) slope.
3. The operation will be carried out in
conformity with the maps and plans as approved.
4. Screening, sifting, washing or crushing of
material native to the site and used for site purposes only, may be permitted
by special permit. All other processing
shall be restricted to the I-Zone only.
5. No machinery, such as a screener, sifter or
crusher, shall be erected or maintained within 100 feet of any property line or
streetline.
6. The existing grade shall be maintained for a
distance of 25 feet parallel to the property line from top (cut) or toe (fill)
of slope. Excavation occurring from 25
feet to 50 feet of a property or street line shall maintain a slope of 1:3
(vertical-horizontal). When deemed
appropriate by the Commission and where a joint agreement between property
owners has been filed with the Commission, an excavation may be allowed to
adjoin adjacent property when such adjointment will not create a hazard and
will provide a more harmonious blend of.
7. No building or other structures shall be
erected on the lot during the operation except temporary shelter for machinery
and portable sanitary facilities, subject to approval by the Commission.
8. At all stages of the operation, and upon
completion, proper drainage shall be provided to prevent collection and
stagnation of water and the prevention of harmful effects upon surrounding
properties through soil erosion or interference with natural watercourses, as
specified in Section 25-27 of these Regulations.
9. The plans shall provide that all access
roads from the project to public highways or streets or to adjoining properties
within 500 feet of such highways, residences or streets maintain a combined 50
feet travel and 50 feet paved entrance/egress to minimize the tracking of soil
on to city and state roads.
10. Proper measures, shall be taken to minimize
the impact on adjacent properties for noise, flying dust or rock, and unsightly
or dangerous conditions. Such measures
may include, when considered necessary, screening, fencing, limitations upon
the practice of stockpiling excavated materials upon the site and shall include
covering truck loads.
11. Whenever any owner, developer or excavator
shall remove topsoil in or upon any land in the city, and is to store said
topsoil, provisions shall be made for the storage of said topsoil within the
boundary of said property. Disturbance
within the preservable section of the area shall be minimized to avoid erosion,
loss of vegetation and windblown material products by means of a seeded
covercrop or other organic mesh covering or seeding process.
12. Except as hereinafter provided, when topsoil
is stored, it shall be uniformly replaced over the entire area or surface of
the land on or before the completion date set forth in the soil removal Special
Exception so that the final grades of said replaced topsoil shall conform to
the proposed final grades shown on the topographical map. In the case of filling operation a layer of
topsoil shall be uniformly placed over the area to conform to proposed final
grades.
13. There shall be no removal, filling, grading
or hauling from any approved project between the hours of 6 p.m. and 7 a.m.,
nor on Saturdays, Sundays or legal holidays.
14. In land excavation operations, the location
of tree stumps and other debris shall be delineated on the site plan.
G. REVIEW CONSIDERATIONS
1. The Commission in considering and reviewing
the application and in arriving at its decision, shall be guided and take into
consideration the public health, safety and general welfare, and particular
consideration shall be given to the following factors:
a.) Soil Erosion by water and wind
b.) Drainage (surface and subsurface)
c.) Soil fertility
d.) Lateral support slopes and grades of
abutting streets and land
e.) Adjacent land values and uses
f.) Potential ground water drinking supplies
g.) Such other factors as may bear upon or
relate to the coordinated, adjusted and harmonious physical development of the
City.
2. In the case of removal of quarry stone and
mining operation, the Commission may modify the foregoing requirements where
such operations will not endanger public health and safety or be detrimental to
the neighboring properties.
3. The Commission may require weekly or monthly
inspection reports on the operations and maintenance program for the proposed
soil erosion and sediment control measures and storm water management
facilities. Such reports shall include:
a.) Phase of areas to be stripped of vegetation;
b.) A weeks schedule of
operations, including starting and completion dates for major improvements,
phases such as clearing, grading, paving, installation of drainage
features.
H. PERMITTING
- EXPIRATION AND RENEWAL
1. Any Special Exception granted under this
Section shall expire two (2) years from the date of Commission approval, unless
specifically granted for a shorter period to time.
2. The Commission may grant renewals of an
approved Special Exception for a period or not to exceed two (2) years,
providing that the operation is being conducted as approved and provided by the
Commission and may determine that a revised or additional performance bond
shall be posted.
3. Before a permit is granted under this
Section the applicant shall post a surety bond with the Zoning Officer in an
amount approved the City Engineer as sufficient to guarantee conformity with
the provisions of the permit issued hereunder.
4. All renewal applications shall be applied
for and shall be subject to all the requirements of this Section. A renewal application shall be treated as a
new application. Site plans for all
renewal applications shall include revised spot elevations. Said spot elevations shall be determined in
the field by a licensed land surveyor.