ARTICLE VI

 

SECTION 25.32  COMPLETION OF EXISTING BUILDINGS

 

 

 

These regulations or any amendment thereto shall not affect any building or its designated use under the following series of conditions and circumstances:

 

a.)   Complete plans for such building or structure legally filed prior to the effective date of these regulations or any amendment thereto affecting such building or structure or the use thereof;

 

b.)   Actual construction begun within ninety days after the building permit was issued;

 

c.)   Structural framework completed within six months after the building permit was issued;

 

d.)   Entire building completed according to the filed plans within two years after the building permit was issued.