BRADLEY ELEMENTARY SCHOOL CONCEPT "A"

FEBRUARY 1999

Item

Unit

Unit Cost

Quantity

Cost

Site Removals

LS

--

Allowance

$1,000

Site Preparation

LS

--

Allowance

5,000

S&E Control

LS

--

Allowance

2,500

Field Expansion (Earthwork)

LS

--

Allowance

50,000

New Parking Area

LS

--

Allowance

25,000

Bathrooms

LS

--

Allowance

30,000*

Topsoil

LS

--

Allowance

10,000

Turf Establishment

LS

--

Allowance

5,000

Miscellaneous Site Improvements

LS

--

Allowance

3,000

Fencing

LS

--

Allowance

20,000

Irrigation/Pump Improvements

LS

--

Allowance

30,000

Landscaping

LS

--

Allowance

3,000

Subtotal

     

184,500

Contingency/Design (20%)

     

36,900

Total

     

$221,400

Total (Rounded)

     

$220,000

 

*Estimated cost budgeted by City of Derby.

 

f23bes-jea.doc

BRADLEY ELEMENTARY SCHOOL CONCEPT "B"

FEBRUARY 1999

Item

Unit

Unit Cost

Quantity

Cost

Site Removals

LS

--

Allowance

$5,000

Site Preparation

LS

--

Allowance

5,000

S&E Control

LS

--

Allowance

2,500

Field Expansion (Earthwork)

LS

--

Allowance

100,000

New Parking Area

LS

--

Allowance

25,000

Bathrooms

LS

--

Allowance

30,000*

Topsoil

LS

--

Allowance

15,000

Turf Establishment

LS

--

Allowance

8,000

Miscellaneous Site Improvements

LS

--

Allowance

5,000

Baseball Infields

LS

--

Allowance

10,000

Light Baseball Fields (relocate existing lights)

LS

--

Allowance

30,000

Light Softball Field

LS

--

Allowance

75,000

Fencing

LS

--

Allowance

30,000

Irrigation/Pump Improvements

LS

--

Allowance

30,000

Landscaping

LS

--

Allowance

3,000

Subtotal

     

373,500

Contingency/Design (20%)

     

74,700

Total

     

$448,200

Total (Rounded)

     

$450,000

 

*Estimated cost budgeted by City of Derby.

 

BRADLEY ELEMENTARY SCHOOL CONCEPT "C"

FEBRUARY 1999

Item

Unit

Unit Cost

Quantity

Cost

Site Removals

LS

--

Allowance

$7,500

Site Preparation

LS

--

Allowance

5,000

S&E Control

LS

--

Allowance

2,500

Field Expansion (Earthwork)

LS

--

Allowance

30,000

New Parking Area

LS

--

Allowance

25,000

Bathrooms

LS

--

Allowance

30,000*

Topsoil

LS

--

Allowance

15,000

Turf Establishment

LS

--

Allowance

10,000

Miscellaneous Site Improvements

LS

--

Allowance

5,000

Fencing

LS

--

Allowance

20,000

Skinned Infields

LS

--

Allowance

8,000

Irrigation/Pump Improvements

LS

--

Allowance

30,000

Landscaping

LS

--

Allowance

3,000

Subtotal

     

191,000

Contingency/Design (20%)

     

38,200

Total

     

$229,200

Total (Rounded)

     

$230,000

 

*Estimated cost budgeted by City of Derby.

 

DERBY HIGH SCHOOL CONCEPT "A"

FEBRUARY 1999

Item

Unit

Unit Cost

Quantity

Cost

Site Removals

LS

--

Allowance

$10,000

Site Preparation

LS

--

Allowance

10,000

S&E Control

LS

--

Allowance

3,000

Field Expansion (Earthwork)

LS

--

Allowance

100,000

New Parking Area/Field Access

LS

--

Allowance

45,000

Fencing

LS

--

Allowance

20,000

Drainage Improvements

LS

--

Allowance

20,000

Walkways

LS

--

Allowance

25,000

Bleacher Improvements

LS

--

Allowance

50,000

Topsoil

LS

--

Allowance

60,000

Turf Establishment (Seed)

LS

--

Allowance

40,000

Miscellaneous Site Improvements

LS

--

Allowance

10,000

Field Lighting Improvements*

LS

--

Allowance

10,000

Irrigation

LS

--

Allowance

50,000

Subtotal

     

433,000

Contingency/Design (20%)

     

86,600

Total

     

$519,600

Total (Rounded)

     

$520,000

 

*Should lighting be provided for the two expanded practice fields, an additional $150,000 should be budgeted.

DERBY HIGH SCHOOL CONCEPT "B"

FEBRUARY 1999

Item

Unit

Unit Cost

Quantity

Cost

Site Removals

LS

--

Allowance

$25,000

Site Preparation

LS

--

Allowance

10,000

S&E Control

LS

--

Allowance

5,000

Field Expansion (Earthwork)

LS

--

Allowance

100,000

New Parking Areas

LS

--

Allowance

50,000

Fencing

LS

--

Allowance

20,000

Synthetic Track

LS

--

Allowance

400,000

Drainage Improvements

LS

--

Allowance

20,000

Walkways

LS

--

Allowance

25,000

Bleacher Improvements

LS

--

Allowance

50,000

Fieldhouse Modifications

LS

--

Allowance

50,000

Topsoil

LS

--

Allowance

85,000

Turf Establishment (Seed)

LS

--

Allowance

40,000

Miscellaneous Site Improvements

LS

--

Allowance

15,000

Field Lighting Improvements/Relocation*

LS

--

Allowance

40,000

Irrigation

LS

--

Allowance

50,000

Subtotal

     

985,000

Contingency/Design (20%)

     

197,000

Total

     

$1,182,000

Total (Rounded)

     

$1,180,000

*Should lighting be provided for the two expanded practice fields, an additional $150,000 should be budgeted.

DERBY HIGH SCHOOL CONCEPT "C"

FEBRUARY 1999

Item

Unit

Unit Cost

Quantity

Cost

Site Removals

LS

--

Allowance

$15,000

Site Preparation

LS

--

Allowance

10,000

S&E Control

LS

--

Allowance

5,000

Field Expansion (Earthwork)

LS

--

Allowance

100,000

New Parking Areas

LS

--

Allowance

50,000

Fencing

LS

--

Allowance

20,000

Drainage Improvements

LS

--

Allowance

20,000

Walkways

LS

--

Allowance

25,000

Bleacher Improvements

LS

--

Allowance

50,000

Soccer Field Lighting*

LS

--

Allowance

110,000

Topsoil

LS

--

Allowance

90,000

Turf Establishment (Seed)

LS

--

Allowance

40,000

Miscellaneous Site Improvements

LS

--

Allowance

10,000

Field Lighting Improvements

LS

--

Allowance

10,000

Irrigation

LS

--

Allowance

50,000

Subtotal

     

605,000

Contingency/Design (20%)

     

121,000

Total

     

$726,000

Total (Rounded)

     

$725,000