Derby Planning School Building Expansion

Referendum - June 10

 City of Derby

Schools Project Summary Sheet

January 19, 2000

This chart shows the cost of the proposed plan including the new high school, the existing high school renovated to a middle school and the athletic facilities within the Ryan Complex. The base cost is shown at the top. The rest of the chart shows the additions made to the base plan by the committee resulting in the final figures at the bottom. The actual costs to taxpayers in Derby reflects the amount that residents will pay after the state share is subtracted from the total cost. (May 2: These figures have been broken down into two questions for the referendum ballot. The ballot questions contain higher figures because of the costs of short term borrowing and fees connected with the bonding. Click here to see the questions.)

It should be noted that new construction is reimbursed at a higher rate than renovations. The athletic fields are reimbursed at half the rate of the school construction.

 

 

 

Actual Project Cost

 

Cost to City after State Reimbursement

 

Basic Schools Construction Project Cost

New High School (9,10,11,12)

Renovated HS into Middle School (6,7,8)

Athletic Fields

 

$36,363,812

 

$20,034,001

 

 

 

 

 

High School Add Alternates (to be added to Basic Project Cost if selected)

 

A

 

Increase B=Ball Court from 84' to 94'

 

$270,000

 

$270,000

 

B

 

Add Choral Room

 

$300,000

 

$300,000

 

C

 

Increase Corridor/Stair width 2'

 

$600,000

 

$600,000

 

D

 

Increase Storage

 

$282,000

 

$282,000

 

E

 

Add Lecture Hall

 

$316,000

 

$316,000

 

F

 

Add 130 space Parking Lot

 

$660,000

 

$211,000

 

Total High School Add Alternates

 

$2,128,000

 

$1,679,000

 

Middle School Add Alternates (to be added to Basic Project Cost if selected)

 

1

 

Add Air Conditioning in Auditorium

 

$75,000

 

$75,000

 

2

 

Add Improvements to Front Courtyard

 

$120,000

 

$120,000

 

3

 

Add Value Engineering deductions back in*

 

$158,000

 

$158,000

 

4

 

Add Planting

 

$25,000

 

$25,000

 

5

 

New wood floor in Gym

 

$88,000

 

$88,000

 

Total Middle School Add Alternates

 

$466,000

 

$466,000

 

Grand Total Schools Project + all Alternates

 

$39,257,812

 

$22,179,001

* revised per meeting 1/17/00